Takt Time, Cycle Time & OEE Calculator
Compute takt time and the three OEE components (availability, performance, quality) from production shift data — the standard lean-manufacturing KPIs.
How to Use the Takt Time, Cycle Time & OEE Calculator
- Enter the available time and customer demand per shift.
- Enter total and good units produced.
- Enter planned downtime and actual runtime.
- Click Calculate.
Casos de Uso
- •Lean manufacturing KPIs.
- •Bottleneck analysis.
- •Shop-floor continuous improvement.
Fórmula
Takt = available time / demand. Availability = runtime / (available − planned downtime). Quality = good / total. OEE = A × P × Q.
Perguntas Frequentes
What is a "world-class" OEE?
The Nakajima benchmark is 85% (A 90% × P 95% × Q 99.9%). Many discrete-manufacturing plants run at 40–60%, so the upside is large.
How is performance defined here?
Performance = (ideal cycle × total units) / runtime. With runtime = ideal cycle × total, the ratio caps at 100%. Feed your own ideal cycle if you track it explicitly.